What a professional home chargepoint site survey should cover

A competent installer should assess the property, proposed charging load and existing electrical installation before fixed chargepoint work is agreed. You can prepare parking, access, usage, equipment, permission and existing-document information without opening electrical equipment. Ask for a written outcome that identifies assumptions, required professional work, the DNO route and any unresolved stop condition.

Institution of Engineering and Technology: Electrical Diversity and Load Curtailment (EVC) webinar questions and answers

Reviewed

Key facts and evidence

As of 13 August 2026, a UK home chargepoint site survey should end in a written professional outcome covering supply capacity, maximum demand, existing equipment, proposed route, load management, remedial work, DNO involvement and permissions. The householder may provide documents and charging needs, but may not open, probe, alter or test fixed electrical equipment.

Institution of Engineering and Technology: Electrical Diversity and Load Curtailment (EVC) webinar questions and answers

Prepare non-technical information for a UK chargepoint survey and ask for a written professional outcome before installation.

Information to prepare

Provide the property type, parking right, preferred charger position, ordinary vehicle-use and charging needs, route preferences, access constraints, other substantial electrical loads or generation, permissions, previous electrical certificates and any DNO correspondence already held. Preparation is documentary and non-contact.

What the written outcome should resolve

Ask the installer to state whether the existing supply and installation are adequate, whether load management, remedial work or a supply change is proposed, which DNO route applies, what permissions and civils remain, and which assumptions could change the price. The professional owns every technical conclusion.

When the survey needs revisiting

Return the proposal to the installer when the charger model, position, route, parking arrangement, property permission, other major load or supply information changes. A quotation based on old site assumptions should not be treated as a current design decision.

What to do next

Use this page to prepare information and evaluate the written survey outcome, not to assess electrical capacity yourself.

Immediate action: Book a site survey with a registered competent EV chargepoint installer before accepting a fixed installation scope.

  • Pause the project if supply or earthing information is unknown, existing equipment is damaged or a required DNO decision is outstanding.
  • Pause if the quote is based on a remote assumption that conflicts with the actual site.

Do not infer from missing evidence

  • Keep all fixed electrical enclosures closed and provide only documents, photographs already available and ordinary site information.
  • Withhold installation approval until the competent installer records a complete site-specific outcome.

Professional hand-off

  • A registered competent EV chargepoint installer or electrical designer should complete the survey and involve the DNO where required.

Questions this record can answer

What does the sourced evidence say about information to prepare?

Provide the property type, parking right, preferred charger position, ordinary vehicle-use and charging needs, route preferences, access constraints, other substantial electrical loads or generation, permissions, previous electrical certificates and any DNO correspondence already held. Preparation is documentary and non-contact.

What does the sourced evidence say about what the written outcome should resolve?

Ask the installer to state whether the existing supply and installation are adequate, whether load management, remedial work or a supply change is proposed, which DNO route applies, what permissions and civils remain, and which assumptions could change the price. The professional owns every technical conclusion.

What does the sourced evidence say about when the survey needs revisiting?

Return the proposal to the installer when the charger model, position, route, parking arrangement, property permission, other major load or supply information changes. A quotation based on old site assumptions should not be treated as a current design decision.